A new clubhouse, ballroom and driving range are being built alongside the 18-hole course.

Architectural impression Rendering of the new clubhouse entrance, driveway, flags and landscaped lawn

Details to be confirmed by JGCC. The same newsletter mentions both a handover by the end of June 2026 and a later developer target of September 2026, followed by fitting out. The current status is to be confirmed by JGCC.

Published progress at 31 March 2026

Overall88%
Driving range98%
Clubhouse and carpark93%
Ballroom and carpark92%

Impression and site, side by side

Architectural impressions show the intended design. Site photographs were published in the club’s January to March 2026 newsletter.

Clubhouse interior

Architectural impression Rendering of a high-ceilinged clubhouse lounge and dining area
Site photo Site photograph of the clubhouse interior during finishing works

Arrival

Architectural impression Rendering of the new clubhouse entrance, driveway, flags and landscaped lawn
Site photo Site photograph of the paved driveway leading to the new clubhouse

Lounge

Architectural impression Rendering of glass-fronted clubhouse lounges along a corridor
Site photo Site photograph of a lounge with its curved bar under construction

Ballroom and driving range

Architectural impression Rendering of the ballroom set with round banquet tables under a chandelier
Site photo Site photograph of the ballroom and driving range building from above

Facilities listed by the club

The club’s membership material lists these facilities as part of the redevelopment. JGCC to confirm which are open now.